Habitat Construction Update - November 2015

Welcome to the latest edition of the Habitat construction update.

The construction of Buildings 1, 8 and the recreation area at Habitat has progressed during October and November with the following works completed and underway:

Basement

  • Suspended services for mechanical, stormwater, sewer and water is continuing.

Building 1 Structure

  • Slab and Block work is complete to Levels 1, 2, 3 and 4. 
  • Level 3 & 4 roof structure is underway. 

Building 8 Structure

  • Slab and block work complete to all levels. 
  • Structural Steel Roof framing complete. 
  • Roof Sheeting underway.

Building 8 Interiors

  • Fitouts nearing completion to  levels 1-3
  • Level 4 Kitchen complete, tiling underway.
  • Level 5 Plasterboard walls underway. 
  • Level 6 External & Internal plasterboard walls underway.

Building 1 Interiors

  • Level 1 Plasterboard complete.
  • Level 2 Plasterboard walls underway.

Pool & Recreation Area

  • Podium, Level 1 slab and pool structure complete. Blockwork complete. 
  • Pool shells complete.

Sales Update
We currently have 95% sold. There are still a few one and two bedroom apartments still available. Please direct all sales enquiries to maddison@stockwells.com.