Construction Update - Habitat

Construction at Habitat West End is well underway. Have a read of what Development Manager Leanne Porter had to say about the project's progress. 

The construction of Buildings 1, 8 and the recreation building (Building 9) at Habitat has progressed during August and into September with the following works completed and underway:

Basement

The basement structure  is complete.  Fit-out of  the basement and installation of services will occur in the coming months. 

Building 1 Structure

Building 1 slab and blockwork  is complete to  Levels 1, 2 and 3. 
Block work has commenced to Level 4. 


Building 8 Structure

Building 8 slab is completed to  Levels 1 to 6 slab.  Construction of the  roof has commenced.

Recreation Room and Swimming Pools

The podium has been poured for the recreation building and mangers unit. The pool structures for the lap pool and plunge pool are complete. The next step will be installing the finishes.  


Building 8 Apartments

The windows and stud work are complete to apartments on Levels 1 to 3.   The plasterboard is complete to  Levels 1 to 2 and has commenced on Level 3. Fit-out of kitchen joinery, tiling, painting and air-conditioners to  all apartments on level 1.   Fit-out has similarly commenced to Level 2.