Habitat Construction Update - January 2016

Investment Property West End
Investment Property West End

Happy New Year and welcome to the latest edition of the Habitat construction update.

The construction of Buildings 1, 8 and the recreation area at Habitat has progressed during December and January with the following works completed and underway:

Building 1

  • All floor slabs and block work is complete
  • Roofing is installed.
  • Level 1: The plaster is complete and the joinery and glazing have both been installed.
  • Levels 1 & 2: the plaster and glazing are also complete. The internal tiling is underway and external tiling is complete. The joinery is fifty percent completed.
  • Level 3: the plasterboard is nearing completion.
  • Level 4: the partition walls are complete and the internal framing is fifty percent complete. The installation of services are also underway.

Building 8

  • All floor slabs are complete.

  • Structural roof and roof sheeting is complete.

  • Levels 1, 2 and 3: almost complete. The final coat of paint will be done and appliances will be installed. Carpet will be installed in the next few weeks.
  • Level 4: the joinery and bench tops have been installed and the tiling has been completed. The plumbing install is well under-way.
  • Level 5: the joinery and bench tops and tiling are underway on Level 5. The external patio tiling is almost complete.
  • Level 6: the glazing has been installed  and the plastering and outdoor tiling is complete.

Pool & Recreation Area

  • The block work to external gardens, recreation room, gym and managers's unit is almost complete.
  • Pool Structure and shell are complete.
  • The Managers unit and structural are underway.

Basement

  • Fire service installation and mechanical ventilation is complete.

Sales Update

We currently have just 8 apartments remaining! Please direct all sales enquiries to amanda@stockwells.com