Habitat Construction Update - April

The construction of Buildings 1, 8 and the recreation area at Habitat has progressed during April with the following works completed and underway:

Building 1

  • Structure including roof is complete.
  • Level 1: Joinery and internal tiling is now complete. Internal painting complete. Carpet installation and external tiling to courtyards still to complete. 
  • Level 2: Joinery and internal tiling is now complete. External tiling to balconies, internal painting and carpet installation still to complete. 
  • Level 3: Joinery and internal tiling is now complete. External tiling to balconies, internal painting and carpet installation still to complete. 
  • Level 4: Joinery complete and internal tiling continues. External tiling to balconies, internal painting and carpet installation still to complete. 

Building 8

  • Structure including roof is complete.
  • Level 1: Units complete. External fencing to courtyards still to complete. 
  • Level 2: Units complete and the builder is currently undertaking unit defect inspection. 
  • Level 3: Units complete and the builder is currently undertaking unit defect inspection. 
  • Level 4: Units complete and the builder is currently undertaking unit defect inspection. 
  • Level 5: Units complete and the builder is currently undertaking unit defect inspection. 
  • Level 6: Units complete and the builder is currently undertaking unit defect inspection. 

Pool & Recreation Area

  • The structure of the recreational facility and managers unit is complete. 
  • Garden planter beds have been filled with soil. Landscaping to commence shortly. 
  • Pool decking is now complete. Tiling and render to recreational areas is continuing.

General Site Update

  • Structure installed for barbecue area & visitor entry.
  • Structure installed for green walls.
  • External fence being constructed.
  • Basement completed. Storage cages and line markings to car parks to be completed.